- Pre-construction: Final design, selection of equipment and materials, assessment and collection of EPC, contract creation and evaluation.
- Construction: Project supervision during the construction phase according to the technical specifications and deadlines.
- Inspection & Delivery Period: Initial and continuous inspection during the first operation period of the park, until the project is fully delivered.
Φωτοβολταικά πάρκα Κύπρος
THE PARKS
The parks are funded by EBRD – The European Bank for Reconstruction and Development (EBRD)
Φωτοβολταικά πάρκα Κύπρος
THE PARK IN DALI
Dali is a grid connected Photovoltaic Plant Project with nominal power of 1,5MWp, in Cyprus.
There are 5773 PV modules RECOM Amur Leopard RCM-260-6PB, with a power of 260Wp each installed. In addition, it provides energy to 28 inverters ABB TRIO-50TL-OUTD-400-SX.
The ALUMIL HELIOS H2100-189-P-25 mounting system supports the PV modules at 25ο and provides a solid base for the entire system.
Also, for every year of its operation, it is estimated that this plant will save about 1.800 tones CO2, equivalent to CO2 emissions of 800 cars
The park is funded by EBRD – The European Bank for Reconstruction and Development (EBRD)
Φωτοβολταικά πάρκα Κύπρος
THE PARK IN NISOU
Nisou is a grid connected Photovoltaic Plant Project with nominal power of 1,5MWp, in Cyprus.
There are 5770 PV modules RECOM Amur Leopard RCM-260-6PB-SW of 260Wp each installed. They provide their energy to 28 inverters ABB TRIO-50TL-OUTD-400-SX.
The ALUMIL HELIOS H2100-189 mounting system will support the PV modules at 25ο. In addition, it will provide a solid base for the entire system. The two poles has been fixed on terrain through bored piles with concrete.
Also, for every year of its operation, it is estimated that this plant will save about 1.800 tones CO2 , equivalent to CO2 emissions of 800 cars.
EBRD – The European Bank for Reconstruction and Development (EBRD) funds the park
THE PARK IN FRENAROS
Frenaros is the biggest Photovoltaic Plant Project in Cyprus with nominal power of 4.4 MWp.
We installed 12.756 PV modules RECOM Amur Leopard RCM-345-6MA-SW of 345Wp each. Also, they provide their energy to 85 inverters ABB TRIO – 50.0 – TL-OUTD.
The ALUMIL HELIOS H2100-189 mounting system will support the PV modules at 25ο and it provides a solid base for the entire system. The two poles are fixed on terrain through bored piles with concrete.
The implementation of this PV park offers multiple social and environmental benefits. In addition, the shifting to ‘green’ generated energy opens additional jobs on the island and makes a significant contribution to protecting the environment.
PV park in the Frenaros area estimates to save about 5,500 tons of CO2 per year, equivalent to CO2 emissions of 2,400 cars per year. Also, more than 1,500 households in the area are powered by the PV Park.
The Green Energy Group, with the completion of this PV Park, one of the largest in Cyprus, is implementing its vision of big energy investments in Cyprus. Also, they are using photovoltaics and strengthens its strong commitment in this direction by making even greater investments in the near future.
EBRD – The European Bank for Reconstruction and Development (EBRD) is funding the park.
THE PARK IN tseri

The project MX Green Energy Ltd 2.78MW is located in Tseri and was put under the Project Management of Suntechnics.
The park utilizes 3.888 Trina Solar 445W-450W Bifacial photovoltaic panels with 445-450Wp power, 15 HUAWEI 185KTL converters and Schletter’s “FS Duo” trackers for optimal performance!
This park will save about 2.522 tons of CO2 emissions each year, which under normal conditions would require 11,587 trees!
Energy saving and the safety of our customers have always been and always will be the priorities of Suntechnics!
6 new photovoltaic parks with a total capacity of 17.82MW
Suntechnics, after successfully completing the two Photovoltaic Parks in Agios Ioannis Malountas, continues to undertake new projects.
Suntechnics has taken over the project management, operation, and maintenance of the six new photovoltaic parks with a total capacity of 17.82MW. The photovoltaic panels have a capacity of 405Watt. They come from one of the best manufacturers of photovoltaic panels in the world, the company, JA Solar. The technology of this photovoltaic panel is Bifacial where it further increases its efficiency by 5 to 10% compared to conventional ones. The single-axis tracking bases (Single Axis Tracker M-TRC-270) that will install the photovoltaic panels are from the well-known company Metaloumin. They will offer an increase in production of 15%. Huawei voltage converters are a pillar of stability and reliability in maximizing solar energy.
With the use of this specific PV system, a significant saving provides carbon dioxide emissions CO2 of 19,186,2 tons per year. Therefore it will require 599,738 trees to absorb them from the environment.
Suntechnics goal is to offer reliability and security to its customers
AstroBank funds the parks, which contbutes to its own way to the restart of the economy in the field of green energy and the environment.